Connect Your Wallets
Connect both Ultra and EVM wallets to start bridging tokens.
Bridge URL: https://bridge.testnet.ultra.io/
Connection Steps
1. Open Bridge Interface
Navigate to Ultra Bridge - you'll see "Connect Wallet" buttons for both Network.

2. Connect Ultra Wallet
- Select Ultra Testnet network
- Click "Connect Ultra Wallet" in Ultra section
- Approve connection in wallet extension/popup
- Verify connection - address and UOS balance visible

3. Connect EVM Wallet
- Select Ethereum Sepolia testnet
- Click "Connect EVM Wallet" in EVM section
- Choose wallet type (MetaMask, WalletConnect, etc.)
- Approve connection in your EVM wallet
- Verify connection - address and token balances visible

Connection Checklist
Ultra Wallet:
- ✅ Connected to Ultra Testnet
- ✅ Address displayed
- ✅ UOS balance visible
EVM Wallet:
- ✅ Connected to Ethereum Sepolia
- ✅ Address displayed
- ✅ Token balances visible
Network Mismatch
If you see network mismatch warnings:

- Use "Switch Network" button if available
- Manually switch in your wallet settings
- Verify correct networks: Ultra Testnet + Ethereum Sepolia
Next Steps
- Ultra→EVM Transfer - Move tokens to Ethereum
- EVM→Ultra Transfer - Move tokens to Ultra
- Resume Transfers - Continue interrupted transfers