EVM → Ultra Transfer ​

Transfer UOS tokens from Ethereum back to Ultra blockchain. Simpler than Ultra→EVM transfers.

Bridge URL: https://bridge.ultra.io/

Transfer Process ​

  1. Approve - Allow bridge to spend your tokens
  2. Transfer - Submit bridge transaction
  3. Complete - Tokens automatically arrive in Ultra wallet

Prerequisites ​

  • ✅ Both wallets connected to correct networks
  • ✅ UOS tokens in EVM wallet (previously bridged)
  • ✅ ETH for gas fees (approval + transfer)

Step-by-Step Transfer ​

1. Configure Transfer ​

  • Verify connections: Ethereum Mainnet + Ultra Mainnet
  • Select UOS token in dropdown
  • Enter amount or use "All" button
  • Set destination: Use connected Ultra address or enter manually
  • Review transaction details

EVM to Ultra Setup

2. Execute Two-Step Process ​

Step A: Token Approval

  • Click "Move Assets"
  • Approve spending cap in EVM wallet
  • Wait for approval confirmation

EVM to Ultra Spending Cap

Step B: Transfer Tokens

  • EVM wallet opens again automatically
  • Confirm transfer transaction
  • Wait for transfer confirmation

EVM to Ultra Transfer Confirmation

3. Transfer Complete ​

  • Tokens arrive in Ultra wallet within ~15 minutes (depending on EVM network congestion)
  • Success message displayed with transaction hash
  • No additional claiming step required

EVM to Ultra Success

Key Differences vs Ultra→EVM ​

FeatureEVM→UltraUltra→EVM
Steps2 wallet confirmationsMultiple stages + claiming
CompletionAutomaticManual "Move Assets" required
ResumeNot availableAvailable if interrupted
ComplexitySimplerMore complex

Important Notes ​

Two-Transaction Process

  • Approval: Allow bridge to spend your tokens (requires ETH gas)
  • Transfer: Actually move the tokens (requires ETH gas)
  • No fees on Ultra side (Ultra has no transaction fees)

Simpler Than Ultra→EVM

  • No manual claiming step required
  • Tokens arrive in Ultra wallet within ~15 minutes (depending on EVM network congestion)

Next Steps ​

  1. Ultra→EVM Transfer - Transfer tokens back to Ethereum
  2. Maintenance Mode - Understanding scheduled downtime
  3. Troubleshooting - Fix common issues

Need Help? ​